Thumbnails

Slideshow (164 photos)

The Hut, Timber Frame (map)
 

Jim holds the temporary brace as the others lower the ridge pole into position

 

Steve's timber framing shop

 

Closeup of timbers on the back porch

 

Bag of webbing uses by the Amstutz crew in assembling the frame

 

The bottom of the posts are sealed before placing them on the metal brackets

 

Up close and personal with the braces

 

Bucket of dowels used hold the joints together

 

Calvin prepares a mortise in the shop

 

Calvin drills a hole for a dowel

 

Calvin uses giant orange hammer to wack something into place

 

Calvin working in the shop on the timbers

 

Carpenter butt

 

Clamping the floor section to the door section

 

Mike climbs the door section

 

Colin pushes scaffolding onto the second floor

 

Colin messing around with the giant hammer, Kevin in the background

 

Comealongs used to hold up sections of the frame during the raising

 

Another comealong

 

Nifty joinery in the timber frame

 

More cool joinery in the timber frame

 

Cool spline holds together a complex joint in the timber frame

 

Boom of the crane during the raising

 

Crane hook flies through the air

 

Hook of the crane

 

Crane moves a load of timbers off the delivery truck

 

Calvin cuts a dowel to make room for the ridge pole

 

Dennis can't resist climbing onto the ridge pole after the raising

 

Skethcy traversing on the ridge pole

 

Doug and Nancy locate the metal brackets on which the posts rest

 

Doug and Nancy locate the metal brackets on which the posts rest

 

Doug and Nancy prep the floor section before it is raised into position

 

Doug working with a clamp during the raising

 

Doug cuts a dowel to length

 

The crane operator directing traffic

 

Doug preps beams for the crane

 

Practiced hands perform the delicate work of moving timbers into place

 

Practiced hands perform the delicate work of moving timbers into place

 

Cutting dowels to length

 

More trimming of dowels

 

Drills sit idle

 

Preparing a large section of the timber frame for lifting by the crane

 

The timber frame without the rafters and ridge pole

 

Framing on the mezzanine floor

 

Section of the mezzanine floor before it was moved into place with the crane

 

The crew prepares to receive the ridge pole

 

Various bents ready to be raised

 

The timber frame, about 1/3 completed

 

The first large bents has just been moved into position

 

The completed timber frame is surrounded by stick-built 2x6 walls

 

Steve and Doug preparing for the first large bent

 

Porch posts partially completed

 

Front porch framing as seen from the front door

 

The completed front porch -- 2x4 T&G white cedar floor, 2x6 T&G white cedar ceiling, cedar posts, and pine timber framing

 

Completed front porch, seen from the west

 

Completed front porch; the yellow wire is for a hanging lantern

 

Completed front porch, seen from the east

 

Front porch posts temporarily held in place

 

Front porch, incomplete, left side

 

Completed front porch seen from the north with the large columns resting on boulders moved from elsewhere on the property

 

Front porch seen from the front (north)

 

Front porch seen from the west; there is a hole where the chinney will soon appear through the roof

 

Another view of the front porch from the west

 

View showing the ceiling of the front porch

 

Front porch posts demonstrating the careful scribing where the posts meet the rock

 

Crew members prepare the floor section to be raised into position

 

Amstutz's shop with Jack making a phone call while Calvin works

 

Jim and Lucie during the raising

 

Jim and Tommy watch the frame raising

 

Jim holds up a brace -- one of the few jobs I could do

 

Jim does nothing, waiting orders

 

Jim connects the strapping to the crane

 

Jim spots the post as it's moved across the site

 

Jim positions a post onto a metal plate on the foundation

 

A post is positioned, making sure that the brace and horizontal member are fit at the same time

 

Jim prepares the straps for lifting a member

 

Jim helping out from the heights

 

Moving about the timber frame is easy for climbers

 

Jim tries to be helpful, but probably is getting in the way

 

Trimming a dowel to the correct length

 

Pounding a dowel into place to hold a joint together

 

Joe and Tommy climb around on the completed frame

 

The "climbers" help position the scaffolding

 

Kevin holds a brace in position while a post is slid into position

 

Kevin clamps a strongback onto a joint to provide lateral strength during lifting

 

The crew getting started with the raising; Steve is dealing with an issue where the iron rods in the foundation are mispositioned

 

Carpenter's level

 

Four strong backs are required to move a rafter subsection

 

Continuing to move the rafter subsection, Doug comes to help

 

Continuing to move the rafter subsection, Doug helps, Jou and Doug watch

 

The very first frame subsection raised into postion -- the king posts around the front door

 

A bucket of comealongs

 

A bucket of tension straps

 

Lucie and Jim on raising day -- all done

 

Lunch on raising day

 

A mallet

 

A mallet and chisel

 

Tools lay about on the site

 

Killer drills

 

Mike positions a post with a spline

 

Mike measures something

 

Mike installs a temporary shim

 

A minor ridge pole is lowers into position

 

Mike gets aggressive with the orange mallet

 

The tenon slides into position in its mortise

 

Steve and Jim move rafters around

 

Nancy planes the end of a post

 

Doug guides a horizontal member into place onto a spline

 

A large subsection of rafters is lifted by crane and positioned around the chimney opening

 

Richard and Tom guide the rafters into position

 

The first ridge pole is moved into position

 

The first bent is moved into position

 

A post flies through space

 

Bits of the timber frame are assembled on the ground before being raised

 

Setting up the straps and comealong in order to pull together the two bents

 

Doug coats the end grain of a post with preservative

 

Raising the final bent

 

The final bent, a little higher

 

The final bent now flies through the air

 

The final bent is lowered into position

 

The finished frame

 

A closeup of the raising crew

 

Another view of the finished frame and crew

 

The red oak used in our timber frame, just after delivery from Rhode Island

 

Raw material in the Amstutz shop

 

Richard attaches a comealong to pull sections of the frame together

 

Pile of sawdust generated during the raising

 

Amstutz's heavy-duty sawhorses

 

Closeup of the scribe work of the left porch post

 

Scribe work of the left porch post

 

The front ridge pole is positioned in place

 

Another view of the front ridge pole being installed

 

All hands on deck for the second ridge pole

 

Securing the second bent

 

The stairwell; no stairs yet, as this is one of the last things to be installed

 

Steve cleans the debris from a mortise

 

Monir adjustments are made to a tenon to ensure a proper fit

 

Steve uses a small tractor to move timbers around his yard and shop

 

Joe and Steve prepare the rafter subsections that surround the chimney

 

Steve and Mike oversee the movement of member

 

Steve and Mike slide the roof truss together

 

Steve inspects a mortise before fitting together the mating members

 

The crane ball is moved into position by Steve

 

Steve uses superhuman strength to casually move a 300 pound post; Kevin looks on in awe

 

Steve does his thing

 

Steve positions a brace as a complicated joint comes together

 

Just before the joint comes together

 

Steve hands something up to Jim

 

Steve straps and Kevin clamps -- preparing to move a section of timber frame with the crane

 

Steve applies straps to a frame section to move with the crane

 

Straps on frame bits

 

Timber frame bits in Steve's shop

 

Braces in Amstutz's shop

 

Lots of timber frame bits await installation

 

More timber frame bits

 

More timber frame bits

 

The entire Hut frame, sitting in storage awaiting installation

 

The timber frame is partially built on the ground prior to the raising

 

The timber frame is partially built on the ground prior to the raising; Lucie sits in the middle

 

Tommy working during the raising

 

Taking a break from the action

 

Working during the raising

 

A small hand-made toolbox

 

Signaling the crane operator to lift using non-standard signals

 

Giant mallets